September 4, 2017
- No work by either contractor
September 5, 2017
Weather: Overcast, cooler temperatures in the mid 60's
General Roofing
- Six roofers on site today
- ISO, densdeck, and membrane was moved to the Elem main office area in preparation for the roof work. This will be the next area to renovate.
- Perimeter edge metal over the admin area was removed.
- New perimeter edge blocking was installed along the admin area
- The parapet wall located on the north Elem roof was flashed in with membrane
Highland Masonry
- Four masons were on site today
- Their work continued on the north side of the Elem.
- Installing sealant on the 2nd floor classrooms continued
- The lower vertical expansion joints along the Elem wind were completed
- The vertical joints along the gym were cleaned out
September 6, 2017
Weather: Cool temperatures reaching 68 degrees, overcast most of the day, no rain
General Roofing
- Six roofers on site today
- The last parapet wall on the Elem wing was flashed in with membrane
- The curbs to all Elem skylights were completed. Membrane was installed on the new curbs in preparation for new skylights which are on order
- Concerns with rain tomorrow may impact roofing over the admin area. Discussed alternative work to take place if rain occurs.
September 7, 2017
Weather: Cooler temperatures reaching 64 degrees with winds reaching 10 mph
General Roofing
- Five roofers on site today
- Roofers debated on starting roof over main office area due to forecast calling for 50% rain.
- At 7:00am they decided to proceed with work over main office
- Wet areas identified on the roof scan were removed over the office suite
- New ISO, densdeck, and .075 EPDM was installed in this location
Highland Masonry
- Four masons on site today
- New sealant installation continued on lower Elem classroom windows
- Installing upper sealant on Elem classroom on north side continued
- Work over the music classrooms and upper boiler room chimney occurred
- Proposal from Highland on IB MC-2 thru IB MC-5 was provided today. Clarification on MC-5 needs to occur before approving