September 17 to September 23, 2017
September 18, 2017
Weather: Hot, muggy, with temperatures reaching 85 degrees
General Roofing
- 5 roofers on site today
- Finished detail work over the Elem library side of the facility. Work included flashing around the two split systems, condensing unit curbs, antenna, and utility chase
- Removed the termination strips under library windows for EPDM to be installed along brick wall.
- Reinstalled the green metal roofing over the main entrance
- Metal wall flashing connecting to the green corrugated front entrance roof needs to be reinstalled.
- Perimeter edge metal over the Jr. High wing was removed. New wood blocking was installed. galvanized fasteners were installed, not stainless steel
Highland Masonry
- Four masons on site today
- Work continued on the vertical joints along the Jr. High wing and around the classrooms
- Discussion on the start date of the auditorium thru wall flashing and brick work. The foreman will call Charlie for details
Willett Builders
- Pay application for material was sent to DO for processing
- Started to set dates for site work and material listing prior to October 9th
September 19, 2017
Weather: Hot, little breeze with temperatures in the lower 80's
General Roofing
- Started with 6 roofers in A.M. then went to four roofers by mid morning
- Started installing ISO, densdeck, and EPDM over the Jr. High wing over the corridor bathrooms and the bump out rooms on the left side.
- Roof drain leaking over Danielle Lucky's room. Found that the coupling has slipped off between the roof drain and pipe. General has been notified to repair the drain
Highland Masonry
- Four masons on site
- Work continues on cleaning out the Jr. High window sealant and vertical joints.
- All old sealant is being removed in this wing. Once completed new sealant will be installed
- Decking was dropped off in preparation for the flashing and brick work to the auditorium wall
Willett Builders
- One technician will be on site tomorrow to estimate materials and confirm conditions so all required accessories for the project can be ordered.
September 20, 2017
Weather: Sunny with little breeze temperatures reaching 84 degrees
General Roofing
- Six roofers on site
- Work over the Jr. High wing continued installing ISO, densdeck, and EPDM
- General Roofing repaired the Elem roof drain that came apart
- There are no plans to ramp up the amount of manpower for the project to expedite the timeline.
Highland Masonry
- Four masons on site today
- Work continued on the Jr High windows along the boiler room entrance
Willett Builders
- Frank Willett was on site estimating the materials for their start date
- The week of October 2nd AHU 1 & 2 will be shut down to evacuate the refrigerant
- The same week, their technicians will start running new pipe from the condensing units to the AHU's.
- The music teachers in the Jr. High wing were notified the classes will need to be conducted on the stage and not their classrooms due to the work.
- October 9th is the mechanical crane lift for the condensing units and coils
September 21, 2017
Weather: Sunny & warm with temperatures in the low 80's
General Roofing
- Six roofers today
- Large section of roofing over the Jr. High wing was completed from the end of the building to the center of the roof.
- New ISO, densdeck, and EPDM was installed in this location. If they do not full secure the membrane today they will complete tomorrow morning.
- Notified me that tomorrow will be a light day of work
- Dumpster will arrive tomorrow that will be located o the dirt access road behind the Elem.
Highland Masonry
- Four masons on site
- Work started on the auditorium brick wall. Brick was removed exposing the improperly installed thru-wall flashing.
- Flashing was found to be short of the brick exposing the center holes of each brick permitting water to enter the facility.
- Work continued on installing backer rod and sealant on the Jr. High wing
September 22, 2017
Weather: Hot & muggy with temperatures reaching 85 degrees
General Roofing
-Six roofers today
- Secured the remaining EPDM installed yesterday
- Clean up of work area (old ISO, left over material, etc)
- New dumpster arrived behind the Elem.
- Roofers left by lunch time