October 15 to October 21, 2017
October 16, 2017
Weather: Cooler temperatures in the mid 50's, overcast, and slight breeze
General Roofing
- Seven roofers on site
- Installed the perimeter edge blocking along the auditorium roof
- Stainless steel fasteners were used to secure the edge blocking
- Material and equipment was moved to the cafeteria/kitchen roof
Highland Masonry
- Five masons on site
- Worked continued on brick and mortar repair at the HS front entrance
- Vertical joint replacement continued on the 2nd floor walls
- The horizontal mortar joint was started over the music wing
Willett Builders
- Four HVAC techs on site
- Work continued on installing the new coil to AHU #1
- New copper piping from AHU #1 to the roof top condensing unit started.
October 17, 2017
Weather: Freezing temperatures early in the morning, temperatures topped out at 61 degrees by the afternoon
General Roofing
- Nine roofers on site
- EPDM replacement on the kitchen/cafeteria roof started
- Perimeter edge blocking installed around the entire kitchen and cafeteria roof
- Discussion between CPL and district on the type of perimeter edge metal (2 piece or 1 piece) versus what was specified in base bid. Warranty letter upholding the existing warranty conditions need to be meet before the product may be specified.
Highland Masonry
- Five masons on site
- Final change order for the HS music wing brick work was submitted
- Corner wall on HS maintenance wing had damaged brick removed.
- HS front entrance work continues, mortar stains removed from existing cultured stone
- Horizontal mortar joint along music wing was cleaned out in preparation for sealant.
Willet Builders
- Five HVAC techs on site
- Work continued on AHU #1 piping, evaporator installation, and controls to unit
October 18, 2017
Weather: Cool morning with temperatures rising to low 60's by mid day
General Roofing
- Nine roofers on site
- Work continued on the cafeteria/kitchen roof, they believe they will have the membrane installed today
- No skylight curb work, detail work or seams on the cafeteria/kitchen roof were completed
- Discussed with John that there are several nails and debris spread out all over the new roof that need to be removed as soon as possible.
Highland Masonry
- Five masons on site
- Work continued on replacing brick along the maintenance corridor exterior wall.
- Repairing brick and mortar joints along the science wing started.
- One set of windows on the 2nd floor of the science wing was found not to be ever sealed from the outside. Contractor will install sealant to protect windows.
- Discussion occurred on the concrete pad replacement outside the HS gym.
Willett Builders
- Two HVAC tech's on site
- Work continued on sweating in the new copper lines to AHU #1 to the condensing unit.
October 19, 2017
Weather: Warmer temperatures in the mid 60's with sunshine
General Roofing
- Nine roofers on site
- Work started on the gym roof.
- Insulation around the roof drains was completely removed. New ISO was installed with densdeck and EPDM
- Additional crickets are to be installed to increase the water flow
- Screws securing the ISO deck were to long as they drilled through the gym ceiling acoustical deck
Highland Masonry
- Four masons on site today
- Work continued on the front entrance brick
- Mortar joints along the classrooms to the science wing are in process of restoration
- The 2nd floor mortar joints/brick replacement continue
- Masons agreed to remove both concrete pads outside the gym at the same time
Willett Builders
- Two HVAC tech's on site
- The contractor did not have the plastic required to keep debris and material from spilling into the Jr. High corridor when removing the insulation and piping to AHU #2
- Work continued on the piping for AHU#1 and the condensing unit
October 20, 2017
Weather: Sunny and warmer in the low 70's
General Roofing
- Nine roofers on site
- 2nd row of ISO, densdeck, and EPDM were installed on the gym roof
- Precautions to minimize the ISO fasteners from drilling through the gym ceiling were made.
- Carlisle Roofing responded to the request by the contractor to use Termiedge for the flashing at the Elem. A two piece material will be used with the exception of the gym roof
Highland Masonry
- Four masons on site today
- Work continued on the science wing mortar restoration and new sealant around the windows.
Willett Builders
- Three HVAC techs on site today
- The insulation was removed from the piping to AHU #2 in the music corridor
- Sweating in the copper lines for AHU #1 continued