October 1 to October 7, 2017
October 2, 2017
Weather: Warm and sunny with temperatures in the mid 70's
General Roofing
- Six roofers on site
- Started replacing membrane around condensing unit #2 over the music rooms.
- New ISO, densdeck, and EPDM were installed in these areas
- Perimeter edge metal samples will be mailed to me to determine what color to install
- Roof drain over room 248 was repaired due to collar slipping apart
Highland Masonry
- Five masons on site
- Work continued over the pool windows where the mortar was being forced out by condensation from the pool environment
- Vertical mortar joints were cleaned out along the gym and maintenance shop
Willett Builders
- Contractor was on site to measure out final material list for project, will return tomorrow
October 3, 2017
Weather: Warmer weather with plenty of sunshine in the mid 70's
General Roofing
- Six roofers on site
- Work continued over the music rooms
- Preparations for the condensing unit replacement were put in place. The EPDM and curbing to the condensing unit are prepared for October 9th work by the mechanical contractor
Highland Masonry
- Five masons on site
- Work continued on the vertical joints along the gym
- Vertical joints along the 2nd floor exterior walls were started.
Willett Builders
- Contractor evacuated the refrigerant from AHU 1 & 2 in preparation for the coil and pipe removal this week.
October 4, 2017
Weather: Warmer with a breeze temperatures reaching the low 80's
General Roofing
- Six roofers on site
- Work over the last of the Jr. High classrooms started.
- Roofers put a roof screw through the electrical feed to 6 Jr. High classrooms around 1:30pm. The maintenance staff will troubleshoot the problem first thing tomorrow morning.
- Samples for the perimeter edge metal were received today
Highland Masonry
- Five masons were on site today
- Vertical joints on the music wing were cleaned out
- Scaffolding was set up for the window work over Superintendent's office took place
- Brick arrived for the front entrance repairs to the HS
October 5, 2017
Weather: Warm temperatures in the low 70's with sunshine
General Roofing
- Five roofers on site
- The last stretch of roofing was installed over the Jr. High classrooms. The roofers will move to the area located over the nurses and teacher lounge
- The roofers and mechanical contractor met to discuss what work needs to be coordinated for Monday October 9th when the new condensing units are installed.
- Perimeter edge blocking was secured with stainless steel fasteners along the Jr. High playground side.
Highland Masonry
- Five masons on site today
- Work started over the Superintendents windows.
- Upon removing the brick veneer over the Supt. windows, discovered there may be another concern then just the flashing.
- Contacted CPL, we agreed to have Highland remove the brick veneer approx. 5' above the windows to expose the steel.
- Vertical joint repair along the music wing continued
Willett Builders
- The coils to AHU 2 were removed with the associated piping located in the penthouse area.
- The piping to AHU 1 was removed
October 6, 2017
Weather: Cooler in the mid 60's with rain
General Roofing
- Five roofers on site
- With rain, the cleaned the work area of debris.
- A few roofers walked the grounds to remove anything that fell off the facilities.
- The color for the perimeter edge metal was picked, Sandstone A-06
- Roofers left by 11:00am
Highland Masonry
- Five masons on site today
- Work on removing the damaged brick at the HS front entrance commenced
- A few of the masons left with the rain during the morning
Willett Builders
- The contractor started removing the coil to AHU 1
- Material for their work arrived, stored in the maintenance shop