November 8 - November 14
November 9
- Massa inserted additional stone behind the HS in preparation for asphalt on Wednesday.
- Mechanical problems with Massa's equipment prevented any further work after 10:00am.
November 10
- Massa finished the installing the stone base and rolling behind the HS gymnasium.
- Top soil was placed along the HS sidewalks and Elem flagpole were excavation occurred in October.
- Relcomm was on sight to resolve the phone issues with the Elem playground emergency phone. Phone now rings the main office.
- Relcomm repaired the HS art room phone that did not operate properly during the phone system conversion.