November 19 to November 25, 2017
November 20, 2017
Weather: Freezing temperatures in the AM, warming up to mid 30's by afternoon
General Roofing
- 6 roofers on site
- Perimeter edge metal started on the Jr. High wing
- Material and equipment was removed from the roof and hauled off site
Highland Masonry
- Two masons on site
- Punchlist work at the HS started.
- HS sills outside cafeteria and maintenance wing were completed
Willett Builders
- Contractor not on site
- Insulator on site to finish AHU #1 pipe insulation
November 21, 2017
Weather: Cooler morning warming up to low 50's by the afternoon
General Roofing
- 6 roofers on site
- The Jr. High perimeter edge metal is finished.
- The parapet walls were competed with termination strips and edge metal.
- Set a date with Brock Alexander to walk the roof for next week. Point out discrepancies and log punchlist concerns before the snow starts to accumulate.
- The expansion joint on the Elem. roof was installed
Highland Masonry
- 2 masons on site
- Continued punchlist work at the HS
- Damaged brick above the maintenance garage door completed
- The sealant around the HS louver where NG lines are located completed
- Discussed starting the Elem. sills and which rooms would be affected. The faculty for those rooms were notified.
Willett Builders
- Contractor not on site
- Insulator had 1-hour worth of work in the penthouse
- Sub- contractor arrived to partially fill both condensing units with refrigerant.
November 22, 2017
Weather: Cooler temperatures in the upper 20's, warming up to the low 30's by mid afternoon.
General Roofing
- 6 roofers on site
- Raised the curbs for the Elem. stairwell skylight and personnel access hatch.
- Grounds were cleaned and debris removed from roof in preparation for the holiday break.
Highland Masonry
- 3 masons on site
- Work started on the Elem window sills
- A total of five sills were removed
Willett Builders
- Contractor not on site
November 23, 2017
- No Contractors on site, Thanksgiving day
November 24, 2017
Weather: Cool with temperatures in the mid 40's
General Roofing
- Contractor not on site
Highland Masonry
- Three masons on site
- Work continued on replacing the defective window sills at the Elem. The sills to the teachers lounge were replaced.
Willett Builders
- Contractor was not on site