November 12 to November 18, 2017
November 13, 2017
Weather: Cool & icy temperatures warming up to mid 30's by the afternoon
General Roofing
- Five roofers on site
- Detail work on the cafeteria/kitchen roof exhaust fans and skylights started.
- General Roofing is expected to keep their contract open to the spring of 2016 for landscaping
Highland Masonry
- Four masons are on site
- The remaining Elem. Aud. brick wall was opened exposing the thru-wall flashing overlaps. The flashing received additional mastic. All joints were inspected prior to water test.
- Water test on the exposed flashing took place in the afternoon. Each joint passed with no leaks into the corridor below.
- Vertical joints at the HS science wing underwent restoration.
- Contractor will be ready for a punchlist on the HS facility by Friday. Meeting set for 9am on Nov. 17
- They still anticipate their work will be completed by the end of Nov.
Willett Builders
- One HVAC tech on site. He started and finished the new victaulic fittings for the circulation pump in the Elem. maintenance shop.
- Contractor plans on keeping the contract open until the spring of 2016 to properly test the new condensing units when the facility has a proper heat load.
November 14, 2017
Weather: Overcast, cool temperatures in the mid 40's
General Roofing
- 6 roofers on site
- Detail work continued on the cafeteria/kitchen roof
- Metal is expected to arrive today
Highland Masonry
- Elem Aud. brick wall was refilled. Contractor needs to repair the damaged vertical sealant joints as a result of the brick removal.
- Caulking of the vertical joints along the teachers lounge at the HS started.
- Minor caulking on vertical joints and window sills continued in preparation for the punchlist.
Willett Builders
- Contractor not on site
November 15, 2017
Weather: Overcast and cool with temperatures in the low 40's
General Roofing
- 6 roofers on site
- Contractor started installing the perimeter edge metal on the kitchen/cafeteria.
- Perimeter edge metal was installed along the teachers lounge roof line
- Contractor indicated they are 100% complete with the cafeteria/kitchen roof & the teachers lounge roof
Highland Masonry
- 3 masons on site
- Walked the HS facility and completing all punchlist work in preparation for the Nov. 17th walk through
Willett Builders
- Contractor not on site
- Frank called indicating that Siemens will be on site tomorrow in attempt to get AHU #2 operating
November 16, 2017
Weather: Rain, overcast and cool temperatures in the mid 30's
General Roofing
- 6 roofers on site
- Extra material was removed from the roof and around the facility and placed in the gravel lot.
- Dumpster was moved by upper playground to avoid any further damage to the grounds
- Detail work and perimeter edge metal was installed on the locker room and gym storage room roof.
Highland Masonry
- Contractor was on site for a few hours and left
Willett Builders
- Contractor not on site
- Siemens arrived today to troubleshoot AHU #2. The damaged Low Limit switch was replaced. Attempts to restart the AHU failed.
- Siemens discovered a electronic valve that had a dead short causing the AHU circuit breaker to continuously trip. The defective component was replaced and the unit is operating as designed.
November 17, 2017
Weather: Cool temperatures in the upper 20's this morning warming up to the upper 30's by the afternoon.
General Roofing
- 5 roofers on site
- The perimeter edge metal was started on the Jr. High roof
- Material and equipment was moved off the roof and loaded on trucks.
- Debris and garbage picked up and deposited in the dumpster
- John indicated additional manpower should be on site next week.
Highland Masonry
- 2 masons on site
- Work continued on the HS cafeteria and guidance office brick walls and windows.
- Performed a punchlist walk through of the HS facility. A list of items was to be corrected was created by CPL.
- Previewed the precast for the Elem. facility. They will store the precast to be installed for the next day in the Elem. maintenance shop to keep warm.
- They anticipate additional manpower next week.
Willett Builders
- Contractor not on site
- One insulator arrived and finished the work on AHU # 2 and started on AHU #4.