- BOE approved the bids for Cogenic and Action Roofing for Phase 1 of the capital project.

May 16, 2013

-Capital project review meeting took place at the Elem./MS library.  In attendance was Dr. Stavisky, Laura Feldman, Dave Walters, Bruce Knapp, Craig Woodworth, and Wayne Fisher.  The three principals stopped in to provide insight during the meeting regarding their respective building.

- Phase 2 scope was reviewed.  The list of alternates and project budget summary was discussed.  Considering an estimated $652,000.00 will be available for alternate work, the existing 5-year plan and energy saving projects were prioritized.  Please look under the "Related Files" tab for the latest "Scope of Work" dated rev. 5/20/13