May 12 - May 18
May 13, 2013
- BOE approved the bids for Cogenic and Action Roofing for Phase 1 of the capital project.
May 16, 2013
-Capital project review meeting took place at the Elem./MS library. In attendance was Dr. Stavisky, Laura Feldman, Dave Walters, Bruce Knapp, Craig Woodworth, and Wayne Fisher. The three principals stopped in to provide insight during the meeting regarding their respective building.
- Phase 2 scope was reviewed. The list of alternates and project budget summary was discussed. Considering an estimated $652,000.00 will be available for alternate work, the existing 5-year plan and energy saving projects were prioritized. Please look under the "Related Files" tab for the latest "Scope of Work" dated rev. 5/20/13