June 29 - July 5

June 30, 2014

- Kircher Construction called to schedule time and date for Alta to review existing conditions for natatorium.  Discussion will include potential bracket extensions in lieu of stainless steel shroud over horizontal linear lighting in the pool area.

- Bethany Technologies submitted pricing for potential upgrades to the existing analog cameras versus installing encoders as specified per the base bid.  The first bid is for 1.3 mega pixel, the second quote is to install 2.0 mega pixel cameras.  The base bid work for the camera installation includes 2.0 interior mega pixel cameras.

July 1, 2014

- J.W. Danforth will be on site July 2nd to review existing conditions in preparation for this summers construction schedule.