December 3 to December 9, 2017

December 4, 2017

Weather:  Cool with temperatures reaching the mid 40's

General Roofing

- Six roofers on site

- Work continued on the detail work on all Elem skylights.

- Detail work on condensing unit # 1 was completed.

- A second coat of mud was installed on the Elem. stairwell skylight damaged earlier on in the project.

- Punch list walk through is set for December 11th

Highland Masonry

- Contractor picked up equipment and materials left from base bid.

- Dumpster will be removed later on in the week

- Punch list walk through is set for Dec. 11th

Willett Builders

- Contractor not on site

- Frank Willett contacted regarding the victaulic fittings recently installed that are now leaking.  They plan to visit the site tomorrow to replace the defective fittings.