August 3 - August 9

August 4, 2014

- Danforth is not on site

- Bethany is not on site

- Kircher continued with the insulating work on the HS 2nd floor.

- Emails and phone calls commenced throughout the day regarding the pool cover submittal.  There are no weights of the blankets wet or dry listed on the Alta shop drawings.  The brackets indicate a 390lb capacity at 36" from wall.  The bracket material does not indicate stainless steel.  Finally, the shop drawings from Kircher do not list the stainless steel cable from the roof joists supporting the bracket.  Kircher provided a letter from an engineering firm stating the proposed bracket by Kircher will properly handle the load.

- Meeting occurred with Edutech and the district on scheduling the wi-fi upgrades to the facilities.  This work will require the network to be shut down.  Dates and delivery times are scheduled.

- The Acrovyn wall panel installation started in the Elem. gym.  The vinyl fabric was removed, door panels prepared and new panels installed.  They anticipate the work will be completed within 2-weeks.

August 5, 2014

- Danforth is not on site

- Bethany is not on site

- Kircher is applying the thermal barrier to the HS 2nd floor insulation today. 

- The acrovyn wall panel installation to the Elem. gym doors continued.

- M/E Engineering provided feed back on the potential phone system upgrades to the district.

August 6, 2014

-Discussion occurred on received change order for additional pool pump to accommodate heat exchanger.  Cost is $6095.00 for pump.  Requested engineer to see if existing pump scheduled to be demoed could be refurbished and reused to save cost.

- Danforth is not on site

- Bethany is not on site

- Kircher continued their work on the Elem. gym door panels

- Today is the final day for the thermal barrier application.  The insulators will clean the area and remove their equipment.  The windows will be partially left open to ventilate the space for the next few days.

August 7, 2014

- Insulators cleaned out HS 2nd floor classrooms.  All their equipment was removed from site.

- Kircher installed the final panels on the Elem. gym doors.

- Requested budgetary cost from Bethany within their scope for overhead projector in the HS auditorium.

- Clarification on the new 3-way valve in the pool heater room and its operation throughout the year was provided to Danforth.

August 8, 2014

- Kircher completed the Elem gym door acrovyn panels.  Equipment was removed from site.

- Danforth was not on site

- Bethany was not on site

- Danforth requested from district a certified roofer to complete 3 penetrations for stacks to accommodate the new booster heaters.