August 25 - August 31
August 26, 2013
Weather: Overcast, with temperatures in the upper 70's. There is a slight drizzle of rain sporadically throughout the day.
- Due to the forecast, Action Roofing is working on detail work around the roof penetrations. A small section of roof (approximately 4 square) over the roof entrance is being reroofed. Considering this section is small, they feel confident they can finish before any hard rain occurs.
- Cogenic is on site to day. Their work consists of draining the two glycol lines to the PoolPak which will be demoed under this project.
- The pool water feed lines to the PoolPak will be drained within the pool filter room sand trap. This will ease their work instead of running hoses to the drain cock to the outside.
- Siemens is on site to disable the controls to the Pool Pak unit.
- Cogenic was shown the disconnect and the main breaker to the Pool Pak. When their ready to shut the unit down, they will deenergize the unit.
The district will hold off on draining the pool until Cogenic is completed with draining the feed lines to the Pool Pak.